MANUFACTURING PROCESS OF STEEL BASE PLATE FOR ZERO TOE LOAD FASTENING SYSTEM

MANUFACTURING PROCESS OF STEEL BASE PLATE FOR ZERO TOE LOAD FASTENING SYSTEM

 

·         Raw Material

After receiving raw material, i.e. rolled plates, inspection and testing to be done according to ‘IRS specification for steel base plates (provisional) 2019’. Results of testing shall be documented in a suitable format and shall be verify with the raw material manufacturer’s test reports.

·         Shearing of Rolled Plates

Accepted rolled plates are to be cut by shearing to length as per drawing. Dimensions to be checked and to be documented in a suitable format.

 

·         Machining

After shearing, machining of 1: 20 cant of blank of steel base plate to be done according to the drawing.Dimensions to be checked and to be documented in a suitable format.

 

·         Forming of Shoulders

Forming of shoulders to be done by hot pressing and edge machining to be done according to the RDSO drawing.Dimensions to be checked and to be documented in a suitable format.

 

·         Welding of Shoulders with Steel Base Plate

Welding of shoulders with Steel Base Plate shall be done according to following Work Instruction.

 

a.      WORK INSTRUCTION FOR WELDING SHOULDER TO STEEL BASE PLATE

 

1.       Process used is Metal Inert – Gas Arc Welding (Gas Metal – Arc Welding) with 100% Carbon-di-

oxide gas as shielding gas.

2.       Welding wire specification is to AWS A5.18, ER 70S6 equivalent to DIN – 8559:SG2/BS 2901 Type A18/IS 6419.

3.       Details of Specification, date of expiry, make of wire shall be checked before opening the reel.

4.       The wire must not be rusted. If the reel has been previously used, the storage should be in polythene cover with specification, date of expiry, make and type recorded.

5.        The shoulder is to be checked for edge preparation.

6.       The surface to be welded shall be cleaned so as to be free from rust, oil, dirt, moisture etc.

7.       Welding shall be done by firm’s approved welders as per IS 7310 (Part 1) & IS 7307 (Part 1).

8.       The shoulders are to be placed on the base plate by using suitable fixtures before welding.

 

Inspection procedure for welding of shoulders with steel base plate shall be done as per following Inspection Procedure.

 

b.      INSPECTION PROCEDURE FOR WELDING OF SHOULDER WITH BASE PLATE

1.      PRELIMINARY STAGE INSPECTION

i)                   All materials used should be to job specification.

ii)                 All materials to be used should be examined for surface, defects, rust, corrosion products, presence of contaminants, laminations etc.

iii)               The welding wire/electrode shall confirm as given in welding procedure manufacturer`s label.

iv)               Qualification test certificate of the welder is to be verified.

v)                 The welding wire/electrode shall be stored and handled with care and in accordance with manufacturer’s recommendation. Wire/electrode that show signs of deterioration, damaged etc. shall not be used.

 

vi)               The welding wire/electrode shall be stored in original packets or cartons in a dry place adequately protected from the effects of the weather.


Previous
Next Post »

2 comments

Click here for comments
juliet
admin
May 26, 2021 at 11:58 PM ×

Excellent post thanks for posting about MANUFACTURING PROCESS OF STEEL BASE PLATE FOR ZERO TOE LOAD FASTENING SYSTEM ,keep posting like this kind of content SAIL TMT Bar manufacturing companie is one of the top leading industry. They are best in supplying all types of steel for building construction.

Reply
avatar
June 16, 2021 at 10:58 PM ×


Best post! It gives me new information about . If your planning to build a structure then JSW roofing sheet dealer in chennai is the best choice and they are one of the leading roofing sheet providers in India. They provide all types of roofing sheets for your home, buildings, and office.

Reply
avatar