MANUFACTURING PROCESS PLAN FOR IMPROVED SEJ WITH 80 mm GAP MAXIMUM ~ MECHTECH GURU

MANUFACTURING PROCESS PLAN FOR IMPROVED SEJ WITH 80 mm GAP MAXIMUM

MANUFACTURING PROCESS PLAN FOR IMPROVED SEJ

(As per Drawing Nos. RDSO/T-6902 & RDSO/T-6914)

 

SL.

NO.

OPERATIONS

PROCESS DESCRIPTION

1)

STACKING OF RAILS

Rails received from the Purchaser / Railway Depot / SAIL are stacked properly in layers with steel spacers between the layers adopting the procedure specified by RDSO.

1.1

VISUAL CHECK AND ULTRASONIC TEST

Ø  Rails are taken out from the stack with EOT cranes using two point slinging and are spread on steel supports. Spread rails are cleaned thoroughly to remove rust, scales and checked visually for surface / rolling defects.

Ø  After visual checking, the rails are subjected to Ultrasonic Test using RDSO approved model of Ultrasonic Rail Tester MSL-32 (R).

Ø  Before testing the rails, the USFD instrument is calibrated with the help of RDSO specified Standard Test Piece.

Ø  Hundred per cent rails are subjected to Ultrasonic testing.

 

1.2

MARKING

Ø  Ultrasonically passed rails are marked with white paint on top of rails.  Then the rails are marked for cutting to required lengths as per Drg. On marking for cutting, a job No. is marked on the top of rail.

Ø  The cast numbers of the ultrasonically passed rails are recorded in a Register and the job number recorded against each.

1.3

CUTTING OF RAILS

Rails marked for cutting are paced on cutting machine on level platform fixed with rollers and cut to the marked length with Hack-Saw / Band Saw machines.  The squareness of the cut end of the rails checked with try-square.

1.4

HEAT TREATMENT

Straightened rails are taken for Heat Treatment / Pearlitised by Induction Heating Process.

1.5

ULTRASONIC TESTING OF HEAD TREATED RAILS

Heat treated rails are further subjected to Ultrasonic and MPT Testing before machining. Heat treated rail also tested for hardness, micro/macro testing & straightening, and mechanical properties.

2)

STOCK RAILS

2.1

MARKING FOR MACHINING

Stock rails after heat treatment and straightening are marked for head and foot machining.

2.2

DRILLING

After straightening the rail are marked for drilling and drilled with radial drill machines.

2.3

MACHINING

a)  NOTCHING – Straightened rails are marked for notching and machining of 

     Head and Foot. Notching of head and foot are done by shaper machines as per marking and checked with checking gauges.

 

 

b)  HEAD & FOOT MACHINING – After notching the rails are taken for head and foot machining on planer machines and machined straight as per marking and are checked with checking gauge.

 

 

c)  RADIUSING AT END – After head and foot machining the rails are taken for   and radius by shaper machines and checked with checking gauge.

2.4

STRAIGHTENING OF STOCK RAILS

Stock rails after assembly are taken for straightening once again before final assembly with tongue rails.


3)

TONGUE RAILS/GAP AVOIDING RAIL/CHECK RAIL

 

3.1

MARKING FOR MACHINING

Tongue rails after heat treatment and straightening are marked for head and foot machining.

3.2

MACHINING

a)  NOTCHING – Straightened rails are marked for notching and machining of Head and Foot.  Notching of head and foot are done by shaper machines as per marking and checked with checking gauges.

 

 

b)  HEAD & FOOT MACHINING – After notching the rails are taken for head and foot machining on planer machines and machined straight as per marking     and are checked with checking gauge.

 

 

c)  RADIUSING AT END – After head and foot machining the rails are taken for end radiusing by shaper machines and checked with checking gauge.

4)

Finishing and Removal of sharp edges

Finishing as per  gauge and removal of sharp edges by filing/ grinding to suitable radius not exceeding 2R

 

5)

ASSEMBLY OF STOCK RAIL WITH GAP AVOIDING RAIL

After complete head and foot machining of the  stock rails and Gap avoiding rail and filing / grinding of sharp edges formed to radius not greater than 2R are assembled together to form the fabricated stock rails using HTS bolts.

 

6)

ASSEMBLY OF SEJ

Final assembly is done in the assembly bay inside the shop floor.  The assembly of finished tongue and stock rails is done by skilled workmen using C.I.  Chairs and M.S. Brackets with T-Head bolts and nuts.  While assembly, hydraulic jim crows are used by aligning the gauge face and matching of tongue and stock rails.

7)

INTERNAL INSPECTION

The final assembly of SEJ and their components are checked by in-house inspection team. The inspection is carried out using steel tape, scale, Vernier Caliper, approved gauges and templates. The observations are recorded in Inspection Register. M&C inspection, Mechanical & chemical testing of components are also done.

8)

EXTERNAL INSPECTION

The products internally inspected and accepted are offered for inspection by the external agencies (RDSO / RITES / Purchaser or their authorized agents).

9)

PAINTING

After inspection and acceptance by the external agency, the products are painted following the procedure as laid in IRS/T-10/2000. 

10)

MARKING

Painted materials are left for drying and then they are marked as per IRS/T-10.

11)

PACKING AND DESPATCH

Inspected, accepted, painted and marked materials are packed in double gunny bags, bundled or lashed with stout wire and dispatched to the Consignee.